| HONEOYE STORAGE CORPORATION |
Status: CLOSED | |
| SSO-12 | Available
Firm Storage Service (FSS) for either 2003-2004 Season or 2003-2005 Seasons Offer Term: January 10 - 31, 2003 |
|
Honeoye Storage Corporation is pleased to announce the availability of 1,200,000 Dth of firm storage service at market-based rates under its Section 284 Firm Storage Service (FSS) Tariff. This firm storage capacity is being offered with specific storage capacities and injection / withdrawal limitations.
Storage Availability:
|
Type
of Service
|
Offering |
|
120-Day
|
1,200,000 Dth
|
Requests for service may be for all or part of this available capacity. Storage services are available for injection commencing on April 1, 2003 at Honeoye's interconnection with Tennessee Gas Pipeline in Ontario County, NY.
Offer Time Frame:
Honeoye Storage Corporation invites offers for this FSS capacity
commencing on January 10, 2003, and extending until 3:00 p.m. (Eastern Standard Time)
on January 31, 2003.
Contract Term
Offers are to be made for service beginning April 1, 2003 and ending either March
31, 2004 or March 31, 2005.
Injection and Withdrawal Limitations:
The following table identifies
the injection and withdrawal periods and limitations associated with each type
of Firm Storage Service being offered:
|
120-Day Service |
||
|
Injection Period |
Inventory Level |
Maximum Daily Injection Quantity |
|
(April 1 to October 31) |
0% to 100% |
1/200 of Maximum Storage Quantity |
|
Withdrawal Period |
Inventory Level |
Maximum Daily Withdrawal Quantity |
|
(November
1 to March 31)
|
100%
- 0%
|
1/120
of Maximum Storage Quantity
|
Fuel and Loss Allowance
A total surface operating allowance of 1.0% shall be retained during injection and withdrawal (1.0% on injection and 1.0% on withdrawal).
Tariff and Minimum Quantities
Potential customers must contract for this Part 284 firm service under terms of Honeoye's Original Volume No. 1a FERC Gas Tariff. Nominations should be made for at least 25,000 Dths of Maximum Quantity Stored. Honeoye will provide all necessary cushion gas.
Minimum Overrun Injection/Withdrawal Rate
The minimum acceptable rate for Overrun Injection and/or Overrun Withdrawal is $0.03 per Dth.
Daily Nominations
Potential customers will be able to withdraw during injection periods and inject during withdrawal periods, but daily nominations will be subject to the operating capability of the Honeoye facility.
Intra-Day Nominations
Potential customers will be permitted to make retroactive intra-day nominations provided Tennessee Gas Pipeline allows such retroactive intra-day nominations or OFO Balancing Agreement is not in effect.
Transportation Arrangements
A customer must make arrangements for gas transportation to and from Honeoye's existing interconnection with Tennessee Gas Pipeline in Ontario County, New York.
Submitting a Formal Bid for Firm Service
A formal bid for the Part 284 service may be made by completing in writing and returning the Storage Service Request Form, to be found herein, together with the supplemental documents and payments specified on that form. Offers should be made according to the procedures outlined in Section 2, General Terms and Conditions of the Tariff. Upon acceptance of an offer, a bidder must execute a Storage Service Agreement in a timely manner.
For Information Contact:
Richard A. Norman
Vice President
Honeoye Storage Corporation
c/o Essex Hydro
55 Union Street
Boston, MA 02108
Tel: 617-367-0032
Fax: 617-367-3796
Email: honeoye@essexhydro.com
James Smoot
Vice President of Operations
Honeoye Gas Storage
4511 Egypt Road
Canandaigua, NY 14424
Tel: (585)229-5161
Fax: (585)229-2015
email: jwsmoot@honeoyestorage.com
Section 2, General Terms and Conditions of the Tariff